Penn Machine Works and its forge shop, US Drop Forge, both now run ShipOS production planning, their president said in a Palantir supplier spotlight on November 16.
Brian Fabian described the pair as "a vertically integrated supplier of forged and machined fittings for the US Navy and the broader maritime industrial base." US Drop Forge makes closed-die forgings in New Jersey. Penn Machine machines them into finished fittings in Aston, Pennsylvania.
Tom Bytheway, Penn Machine's naval project manager, named Electric Boat as "our main navy customer." He said roughly 65% of the material for its Navy jobs comes from US Drop Forge. Fabian said ShipOS started at Penn Machine alone, expanded to US Drop Forge with the Navy, and is now expanding to sister company Western Forge and Flange.
Kara Li, Palantir's ShipOS engineering lead, said the tool slots operations into the schedule by operation sequence, job due dates and work center capacity. It then alerts planners when something changes. Once suppliers are connected, she said, updates can flow automatically across the network.
In a demo on notional data, a delay at the forge surfaced in Penn Machine's schedule. Bytheway added a temporary shift to keep his job on time.
ShipOS is the Navy's program with Palantir. Its December 2025 announcement said it "authorizes up to $448 million." Samantha Rye of the Navy's DRPM Submarines office said the program expects to reach capacity by the end of the year, while Li said January. The two timelines do not match.
The spotlight does not say who pays for supplier onboarding. Palantir's Mike Gallagher said the aim was for companies to take on sustainment costs after the two-year program, Breaking Defense reported.
In our view, a forge and a machine shop sharing one live schedule shows ShipOS working below the prime yards, much as Changshin took Foundry onto its factory floor. We think the thing to watch is who funds supplier deployments like this one when the two-year program ends.