Palantir says customers can expect streaming ingest compute costs on Foundry worker to fall by around 97.5% from November 1, 2026. For teams currently using agent worker, getting there means moving a whole source off it.
The claim is in Palantir's November 2026 announcements, dated November 5. "From November 1, 2026, customers can expect to see a reduction of around 97.5% in compute costs for their streaming ingests when running on Foundry worker compared to what it would have been previously," Palantir says.
Foundry News reported the announcement on November 5. This guide covers the hands-on part: moving a source to Foundry worker, fixing common failures and knowing where to review compute afterwards.
Why this matters now
"Foundry worker is the recommended method for accessing external systems and replaces the legacy agent worker," the November announcement says. Palantir describes the price cut this way: "This is intended to facilitate migration from agent worker to Foundry worker."
Its advice to streaming teams is plain: "If you are currently using agent worker for streaming ingests, we recommend migrating as soon as possible."
The cut follows the October 2026 announcements. That release said several Foundry worker operations would no longer incur compute costs from August 2026. It also said: "Streaming ingests will continue to be billed."
In our view, the November cut gives streaming teams a strong cost reason to plan their migration now.
What changes on Foundry worker
Palantir's Foundry worker vs. agent worker guide explains the execution model. "Foundry worker runs each capability in its own container, sized to the job," it says. "Compute scales independently per job, rather than being bounded by the capacity of a single agent host."
Agents keep a narrower role. "Agents now act only as network proxies via agent proxy egress policies; they no longer execute capabilities," the guide says.
With agent proxy, Palantir says the network model does not change: "With agent proxy, the agent still initiates an outbound WebSocket to Foundry, and all traffic to your source systems still originates from the agent inside your network — no new inbound paths into your network, same model as agent worker."
The guide asks whether Foundry worker is as performant as agent worker. Its answer: "Yes. Containerized jobs do not compete for a single agent's heap and can scale per job."
New features go to Foundry worker. "New capabilities and ongoing feature development target Foundry worker only," the guide says.
Existing setups keep running for now. "Existing agent worker sources will continue to work. Agent worker is legacy, fully supported," Palantir says.
Before you start
Palantir's migration guide sets out what you need. It also warns of a stoppage you should plan for.
- A healthy agent. "You have at least one healthy agent assigned to the source that can supply source secrets, certificates, and, if applicable, JDBC drivers."
- Egress permissions. "To create new egress policies, you must have access to the workflow titled Manage network egress configuration in Control Panel, which is granted to the Information Security Officer role."
- A maintenance window. "All running jobs (syncs, exports, tasks) will be terminated as part of the migration," Palantir says. This applies to everything running on the source, not to one stream.
Step by step: migrate a source
These steps follow the order in Palantir's migration guide.
- Open the migration dialog. "Navigate to Connection settings > Connection details and select Compute: Agent worker. This opens a dialog where you can select Migrate to Foundry worker."
- Choose a representative agent. "Select a healthy agent currently assigned to the source. The selected agent is used to copy secrets and certificates to Foundry and to suggest required egress configuration based on the agent's current setup."
- Copy certificates to the source. "With Foundry worker, certificates must be applied directly to the source rather than to the agent."
- Configure a JDBC driver, if needed. Palantir lists this step as optional, needed only when the source type requires a driver.
- Add egress policies. "Configure direct connection or agent proxy egress policies to define how the Foundry worker should reach your source systems."
On choosing between the two egress types, Palantir advises: "Use either a direct connection for systems accessible from Foundry, or an agent-proxy connection for sources hosted on separate networks."
After the switch, "Scheduled jobs will run in Foundry on the next scheduled run, but unscheduled jobs must be manually restarted," Palantir says. We suggest one extra step of your own. Open every job on the source, streaming ingests included, and confirm each one is running again.
Switching manually, or going back
You can skip the wizard. "When switching manually, credentials must be re-entered, as the automated secret transfer from the agent is not performed," Palantir says.
You can also undo the move. "For 30 days after a migration, you can revert the source to its previous agent worker configuration," the guide says. Go to Connection settings > Connection details on the migrated source, then select Agent worker > Revert in the Compute dropdown.
A revert restores the pre-migration connection settings. "All connection settings, including credentials, will be reverted to the state before migration. Any changes made since will be lost," Palantir says.
When the migration fails
Palantir's guide lists four errors and their fixes:
- `Could not resolve type id as a subtype of 'com.palantir.magritte.api.Source'`: "Ensure that you have configured all required certificates, proxies, and drivers required for a particular source, then retry the migration."
- `UnknownHostException`: "Ensure that correct egress policies are assigned to the source."
- `Driver class not found`: "Confirm that the correct driver is uploaded to the JDBC source."
- `PKIX path building failed`: "Ensure that correct certificates are added to the source."
Each fix points back to certificates, drivers or egress policies, which are steps 3 to 5 above.
Where to review compute
Palantir's November announcements also introduce a new usage and limits page. "It covers only traffic reported through Foundry's rate limits infrastructure and does not represent all compute, storage, or billable usage. To analyze those, continue to use the Overview and Analysis pages in Resource Management," Palantir says.
So the Overview and Analysis pages are where Palantir points you to review compute.
Checking the saving on your own enrollment
Palantir describes the reduction as roughly 97.5%, an expectation measured against what costs would have been before. Our earlier story noted that the announcement does not give a baseline price, a new rate or a pricing unit.
We think the most reliable check is your own enrollment. Review compute in Overview and Analysis once your sources have moved. Avoid changing other parts of the pipeline at the same time, so the effect of the migration stays easy to see.
If your figures raise questions, Palantir invites feedback through Palantir Support or its Developer Community, using the data-connection tag.
Watch out for
- Source-wide stoppage. Palantir says migration terminates all running jobs on the source.
- Unscheduled jobs. Palantir says these must be restarted manually.
- Permissions. Palantir says creating egress policies needs the Manage network egress configuration workflow, granted to the Information Security Officer role.
- Certificates. On Foundry worker, Palantir says, they go on the source, not the agent.
- Manual switching. Palantir says you must re-enter credentials.
- Reverting. Palantir says changes made since the migration are lost.
- The usage and limits page. Palantir says it does not represent all compute, so do not treat it as your full cost picture.
Our take
In our view, the guided wizard and the 30-day revert make a staged move practical. We would start with a source that serves one well-understood stream. Schedule it for a quiet window, because every job on that source stops, and confirm everything restarts before moving the next source.
What to watch: your own compute in the Overview and Analysis pages over the first full months after November 1, and new data-connection entries on Palantir's announcements pages.